Guangda Shayang Waste Incineration Power Generation Project passes “72+24” trial operation
2021-4-24 15:38:51
At 18:30 of April 23, Guangda Shayang Domestic Waste Incineration Power
Generation Project smoothly passed “72+24” trial operation, and smoothly
realized Grid connected power generation.
The project, which is located in Gaoyang Village, Gaoyang Town,
Shayang County, Jingmen City, includes 1×400t/d mechanical grate furnace and
1×7.5MW medium temperature and medium pressure pure condensing turbine
generator unit. After the project is completed, it will process 133,300 tons of
urban domestic waste, generate approximately 51.34 million kilowatt-hours
electricity, and reduce about 72.8 tons emission of sulfur dioxide, 31.2 tons
emission of nitrogen oxides and 9400 tons emission of dust annually. It has
significant social, environmental and economic benefits, and greatly promotes
local economic development.